Second Coat

Lightly sand the first coat.

Check the Level of Finish required in the architects’ specification, before applying the second coat as detailed in Plasterboard Finish Selection.

Apply a second coat of BGC Base Coat 180mm wide over the joints, making sure to feather out the edges.

Apply a second coat to all fasteners and damaged areas, feathering out by about 25mm.

Allow the second coat to set and dry for a minimum of 24 hours or 1 hour for setting type cements (or as per compound manufacturer’s recommendation).

Second or Third Coat

Third Coat

Lightly sand the second coat.

Apply a thin finish coat of BGC Top Coat centrally over second coat, after it has set and hardened. Dampen the outer edges of the finish coat, with a sponge to feather out the BGC Top Coat about 280mm approx wide.

Apply a thin final coat of BGC Top Coat over all fasteners and damaged areas.